01 / Scope of Work
Work modelled, designed or delivered.
- 01
Developed and reviewed an 8,760-hour hospital demand model with 1.20 MW peak demand, 780 kW average demand and a 650 kW critical-load requirement.
- 02
Modelled grid availability at 18 hours/day and assessed a defined four-hour outage window against the requirement for uninterrupted critical-load supply.
- 03
Evaluated PV capacities up to 1.2 MW, battery storage up to 2.5 MWh and PCS capacity up to 1 MW using HOMER techno-economic optimization.
- 04
Compared dispatch strategies and selected the lowest-NPC feasible architecture meeting the critical-load reliability requirement.
- 05
Developed the recommended architecture in ETAP, including PV, battery/PCS, grid interface, two diesel generators, critical and non-critical hospital loads.
- 06
Reviewed ETAP time-series load-flow behaviour and system operating quantities for the modelled electrical network.
- 07
Prepared annual demand, load-duration, monthly demand, monthly energy and outage-availability visualisations to communicate the engineering basis of the study.



